In Aubrey, the permit question is triggered by the vegetation itself. The city's subdivision ordinance requires a Site Development Permit before any site development work that affects vegetation or tree removal, erosion control, storm drainage or a floodplain, and it applies in the city and its extraterritorial jurisdiction. That reach into the ETJ is what most owners miss. For [Homestead Land Clearing](https://homesteadlandclearingfrisco.com/), land clearing in Aubrey, TX starts by sorting out whether a job is site development, and if so, getting the pre-construction conference on the calendar before any 6-inch tree comes down.

## How Aubrey's rules shape the work

<KeyTakeaways items={["A Site Development Permit covers vegetation removal in Aubrey and its ETJ, with a pre-con meeting before clearing trees over 6 inches.", "Burn permits are issued only after a site inspection and are good for the day of issue.", "Residential burn permits are free; a commercial burn permit is $2,000 for seven days.", "Sandy Cross Timbers soils carry equipment well when wet but wash on slopes."]} />

**The permit sequence.** Under the subdivision ordinance, every contractor attends a pre-construction conference before the permit is released and before any clearing, filling, excavation or removal of trees larger than 6 inches in caliper. Erosion controls and tree-protection devices must be in place to the City Engineer's satisfaction first. A published Aubrey tree mitigation table was not found, so no mitigation rate is assumed. For subdivision or [commercial land clearing](https://homesteadlandclearingfrisco.com/commercial-land-clearing/), this conference sits between the plan approval and the first machine.

**Burning is possible, with conditions.** Aubrey's outdoor burning article requires a Fire Department permit approved by the fire chief, issued only after the site is inspected and valid only on its day of issue, 8 a.m. to sundown. The burn must sit downwind of and at least 300 feet from structures with sensitive receptors on adjacent properties, or 50 feet with the neighbor's notarized approval. Wind must be 6 to 20 mph, and the department sets pile size. A county burn ban binds the city. Residential permits are free; a commercial permit is $2,000 for seven days, which often tips a commercial job toward [debris removal](https://homesteadlandclearingfrisco.com/land-clearing-debris-removal/) or mulching. The [Collin and Denton burning guide](https://homesteadlandclearingfrisco.com/guide/burning-brush-collin-denton-county/) explains how county bans work.

## How an Aubrey job usually runs

1. **Walk the property:** boundaries, trees to keep, slopes, wet spots, fences, and what is buried or overhead.
2. **Check the rules for that address:** city or ETJ, whether the work counts as site development, burn options, floodplain limits and Texas811 locates.
3. **Write the scope:** method, finish level, stumps, debris plan and erosion control, in writing, before a price.
4. **Clear and hand off** at the agreed finish, ready for the next trade or for seeding.

## Reading Aubrey ground

Aubrey sits on the Cross Timbers side of the county line, and its ground behaves differently from the clay east of Frisco. USDA NRCS soil data around Aubrey, Pilot Point and Cross Roads shows Gasil fine sandy loam, Silstid loamy fine sand and similar well-drained sandy loams, with the Birome-Rayex-Aubrey complex on 2 to 15 percent slopes. Sandy ground carries tracked equipment better after rain than Houston Black clay does, but loose sand on a slope washes fast once the cover is gone. Silt fence and seeding belong in the scope on those tracts, as the [erosion control guide](https://homesteadlandclearingfrisco.com/guide/erosion-control-after-land-clearing/) explains.

The vegetation follows the soil. Texas Parks and Wildlife describes the East Cross Timbers as post oak and blackjack oak woodland with cedar elm and hickory, plus eastern red cedar, mesquite, bois d'arc and greenbriar. On that kind of tract, [selective clearing](https://homesteadlandclearingfrisco.com/selective-clearing/) that removes cedar and understory while keeping the oaks is often the realistic scope, and [forestry mulching](https://homesteadlandclearingfrisco.com/forestry-mulching/) leaves the ground cover a sandy slope needs.

Growth shows in the permits: Census counted 128 single-family permits in Aubrey in 2024 and 396 the next year. Subdivision tracts that disturb an acre or more fall under TCEQ's construction stormwater permit, covered in the [stormwater permit guide](https://homesteadlandclearingfrisco.com/guide/stormwater-permit-for-land-clearing/).

## Nearby towns with their own rules

### Pilot Point

Pilot Point's online code shows no tree removal permit or mitigation requirement. Its landscape rules protect trees an owner keeps on a construction project, flagged with orange tape and fenced to the drip line where required. Its open burning article was repealed in 2016, and burning now falls under fire code amendments kept on file with the city secretary, so burn conditions are confirmed with the Fire Marshal. Census counted 520 and 573 single-family permits there in 2024 and the year after, more than Aubrey itself. The town sits near Ray Roberts Lake, whose state park TPWD describes as dense post oak, blackjack oak and elm groves.

### Cross Roads

Cross Roads protects trees 6 inches and larger, except listed species including mesquite, hackberry, cottonwood, willow and eastern red cedar. Its rule does not apply within 3 acres around a built primary dwelling. Elsewhere on residential or agricultural land outside commercial corridors, owners may remove 7 percent of total protected caliper inches a year and 21 percent in any 5 years, and trees 18 inches or larger need Town Council approval. The 3-acre exemption carries a one-year look-back if the land's use changes. A large [pasture clearing](https://homesteadlandclearingfrisco.com/pasture-clearing/) plan there may run over several years.

### Providence Village

Providence Village uses the same 7 percent and 21 percent caps, requires a tree removal permit before any protected tree is removed, and exempts mesquite, thorny honey locust, cottonwood, cedar, hackberry and willow. [Brush clearing](https://homesteadlandclearingfrisco.com/brush-clearing/) of cedar and mesquite there faces far fewer limits than removing an oak. The town's rules also keep construction traffic out of protected trees' critical root zones, with exceptions for clearing underbrush and pad grading, so the access route for a machine is drawn before it arrives.

Aubrey and its neighbors share sandy ground but not rule books. A [quote that lists the permit steps](https://homesteadlandclearingfrisco.com/guide/what-a-land-clearing-quote-should-include/) saves surprises, and if the land carries an agricultural valuation, read the [ag valuation guide](https://homesteadlandclearingfrisco.com/guide/ag-exemption-and-land-clearing/) before clearing it. [Get in touch](https://homesteadlandclearingfrisco.com/contact/) to start.

## Frequently asked questions

### How much does an Aubrey burn permit cost for land clearing debris?

Aubrey's fee schedule lists a residential burn permit as free, issued after fire personnel inspect the site, and a commercial burn permit at $2,000, valid for seven days from issuance. On a commercial clearing job, that fee is weighed against mulching or hauling the material instead.

### Does clearing land in Aubrey's ETJ need a city permit?

On site development work, yes. Aubrey's subdivision ordinance requires a Site Development Permit before any work in the city or its extraterritorial jurisdiction that affects vegetation or tree removal, erosion control, storm drainage or a floodplain. Contractors attend a pre-construction conference before clearing or removing trees larger than 6 inches in caliper.

### How close to my neighbor's house can an Aubrey burn pile be?

At least 300 feet from structures with sensitive receptors on adjacent properties, and downwind of them. With the adjacent owner's notarized written approval, the distance can drop to 50 feet. The permit is valid only on its day of issue, wind must be 6 to 20 mph, and a county burn ban overrides it.

### Does Cross Roads limit how many trees I can clear on my acreage?

Yes, outside its 3-acre exemption around a built primary dwelling. On residential or agricultural property outside commercial corridors, Cross Roads allows removal of 7 percent of total protected caliper inches per year and 21 percent in any 5 years. Any protected tree 18 inches or larger needs Town Council approval.

### Is there a tree removal permit in Pilot Point?

None was found in Pilot Point's online code. Its landscape rules protect trees an owner chooses to keep during construction, with orange flagging and drip-line fencing when the building official requires it. The online code may not show every requirement, so the answer is confirmed with the city for the specific address before work starts.